Knocksense Shorts | 84-meter tunnel on Kanpur Metro underground corridor completed

Beyond this, about 5 km long elevated section from Baradevi to Naubasta will be constructed.

Sagar Purswani

The construction of 23 km long Corridor-1 of the Kanpur Metro Rail Project (IIT to Naubasta) is in progress. Moving up the ladder, the UPMRCL has finally completed the tunnelling of an 84-meter of underground metro rail section.

The Corridor-1 has a 4 km long underground section between Chunniganj to Nayaganj where the tunnelling process is being conducted with the help of a Tunnel Boring Machine.

Since July 4, 60 rings in the tunnel have been installed. Due to this, the TBM will be able to move at a speed of about 12 to 15 meters per day. Furthermore, a total of 940 meters long tunnel will be constructed from Bada Chauraha to Nayaganj. Beyond this, about 5 km long elevated section from Baradevi to Naubasta will be constructed.

To get all the latest content, download our mobile application. Available for both iOS & Android devices. 

Lucknow’s NYE lineup is stacked | 7 parties & events to ring in 2026!

Pet Parents in India! Checkout THIS ultimate flight guide for a stress-free journey with pets

Fair fares, finally! Mumbai Airport to get prepaid auto-rickshaw service at T1 & T2 from June 2025

New Year Resolution No. 1 for Lucknow: Experience alcohol shopping the premium way at Just Madira

9 events in Mumbai that will make you step out this December

SCROLL FOR NEXT