If you have been rather curious about the status of India’s much-anticipated Bullet train project, there’s news for you. The Indian Railway Ministry recently released a comprehensive update on the progress of the Mumbai-Ahmedabad Bullet train corridor which is presently under development.
As per the latest update released by the Indian Railway Ministry via its official Twitter handle, the overall physical progress of the bullet train project was reported to be at 26.33% as of February 28, 2023.
Construction kicks off for the Bandra-Kurla Complex Station development
#BulletTrain Project (As on 28.02.23)
Overall Physical Progress: 𝟐𝟔.𝟑𝟑%
Gujarat
Overall📈:32.93%
Civil Works:54.74%Maharashtra
Overall📈:13.72%🏗️Pile work: 257.06 Km
🏗️Pier work: 155.48 Km
🏗️37.64 Km Girders launched
🌲8003 trees transplanted
🌱83,600 saplings planted pic.twitter.com/0qntHKykoa— Ministry of Railways (@RailMinIndia) March 14, 2023
The ministry’s update further highlighted that the state of Maharashtra has completed approximately 13.72% of the total work required for the project. Meanwhile, Gujarat has made significant progress in the civil work area, with more than 52% of the work already completed, and an overall completion rate of 36.93%.
In addition, a joint venture of Hindustan Construction Company Ltd (HCC) and Megha Engineering & Infrastructures Ltd has recently won the contract for the construction of Bandra-Kurla Complex Station as part of the Mumbai-Ahmedabad Bullet train project.
Reportedly, the station will be the only underground station on the high-speed rail corridor which will be constructed at a depth of 24 meters (approx.) below ground level, and its development is now underway
“24x7x365 work” underway on the High Speed rail corridor
24x7x365 work #BulletTrain
23rd Feb: Piers 152.32 Km
(+0.52Km)
24th Feb: Piers 152.88 Km
(+0.56 Km)
25th Feb: Piers 153.48 Km
(+0.60 Km)
26th Feb: Piers 153.88 Km
(+0.40 Km) pic.twitter.com/QVdhYTu56m— Ashwini Vaishnaw (@AshwiniVaishnaw) February 27, 2023
Earlier this Feb, Railway Minister Ashwini Vaishnaw took to Twitter sharing insightful pictures of the ongoing construction work and highlighted the “24x7x365 work” happening on the project. Additionally, Vaishnaw shared data showing the progress made on the elevated route between February 23 and 26.
Reportedly, the Mumbai-Ahmedabad Bullet train project is scheduled to start operations in 2027, with a trial run planned between Surat and Billimora in Gujarat in August 2026.
Mumbai-Ahmedabad bullet train project to accommodate India’s 1st undersea route



















